P.27 of the Textbook indicates that one of the purpose of tailoring should be that "the project management method used is appropriate to the project (e.g. aligning the method with the business processes that may govern and support the project, such as human resources, finance and procurement)". However, project is different from the project's environment.
I would thus also go for C.
Shoul be C?
Pag. 27 of the official guide
Tailoring requires the project board and the project manager to make proactive choices and decisions on how
PRINCE2 will be applied. When tailoring PRINCE2, it is important to remember that effective project
management requires information (not necessarily documents) and decisions (not necessarily meetings).
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
TaiH
10 months, 1 week agoomande
1 year agomajoy010190
1 year, 1 month agosdoukkal
1 year, 8 months agosdoukkal
1 year, 8 months agoKing_Laps
2 years agomazzantiemanuele
2 years, 8 months ago