According to the 'tailor to suit the project' principle, what is the basis for effective project management?

  • A. That the appropriate number and type of meetings are held
  • B. That the project is divided into an appropriate number of stages
  • C. That the appropriate information is provided to make decisions
  • D. That the project method relates to the project's environment
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
TaiH
10 months, 1 week ago
Selected Answer: C
should be C, same reasons others have mentioned already
upvoted 1 times
...
omande
1 year ago
Selected Answer: C
P.27 of the Textbook indicates that one of the purpose of tailoring should be that "the project management method used is appropriate to the project (e.g. aligning the method with the business processes that may govern and support the project, such as human resources, finance and procurement)". However, project is different from the project's environment. I would thus also go for C.
upvoted 1 times
...
majoy010190
1 year, 1 month ago
Why D should be the correct answer?
upvoted 1 times
...
sdoukkal
1 year, 8 months ago
Selected Answer: C
To me correct answer is C
upvoted 1 times
...
sdoukkal
1 year, 8 months ago
I was expecting C to be the right answer .
upvoted 1 times
...
King_Laps
2 years ago
the correct answer is C
upvoted 1 times
...
mazzantiemanuele
2 years, 8 months ago
Shoul be C? Pag. 27 of the official guide Tailoring requires the project board and the project manager to make proactive choices and decisions on how PRINCE2 will be applied. When tailoring PRINCE2, it is important to remember that effective project management requires information (not necessarily documents) and decisions (not necessarily meetings).
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.