To be following PRINCE2, a project must, as a minimum:
● define its quality management approach. This approach must minimally cover:
● the project’s approach to quality control
● the project’s approach to project assurance.
Beware that project assurance is different from quality assurance.
D. To define the project's approach to quality assurance
One of the minimum requirements for applying the quality theme in PRINCE2 project management is to define the project's approach to quality assurance. This includes specifying how quality will be managed and assured throughout the project to meet the project's quality requirements and standards.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
test235
11 months, 1 week agoomande
1 year agofgtfgtet4r56y
1 year, 1 month agoLynl
2 years, 8 months agoLynl
2 years, 7 months ago