During previous projects, stakeholders became confused when using a number of separate project registers. Therefore, when preparing the risk management approach, the project manager created a risk register template and added it to an integrated project register. This register is a spreadsheet that includes project assumptions, issues, dependencies, and now risks, on separate pages.
Is this appropriate for a risk register, and why?
HelgeFFM
10 months agoravi_aws
1 year, 1 month agoManikRoy
1 year, 2 months agoPieroBe
1 year, 4 months agoPrincessOfHess
1 year, 10 months agoanti8
2 years, 9 months ago