Exam PRINCE2-Foundation topic 1 question 342 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 342
Topic #: 1
[All PRINCE2-Foundation Questions]

From which perspective does the 'managing product delivery' process view the project?

  • A. Corporate, programme management or the customer
  • B. Project board
  • C. Project manager
  • D. Team manager
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference:
https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-managing-product-delivery-process-in-prince2

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 5 days ago
D = correct; Why other options are not correct: A. Corporate, programme management or the customer: This is a higher-level perspective focused on the overall project objectives and benefits. B. Project board: This perspective focuses on overall project direction and decision-making. C. Project manager: While the project manager is involved in this process, the process itself is viewed from the perspective of the team manager who is doing the work.
upvoted 1 times
...
themvp9
2 years, 9 months ago
Correct: Managing product delivery views the project from the team manager’s perspective, whereas the controlling a stage process views it from the project manager’s perspective.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...