D = correct; Why other options are not correct:
A. Corporate, programme management or the customer: This is a higher-level perspective focused on the overall project objectives and benefits.
B. Project board: This perspective focuses on overall project direction and decision-making.
C. Project manager: While the project manager is involved in this process, the process itself is viewed from the perspective of the team manager who is doing the work.
Correct:
Managing product delivery views the project from the team manager’s
perspective, whereas the controlling a stage process views it from the
project manager’s perspective.
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week, 5 days agothemvp9
2 years, 9 months ago