How should a risky and complex project be planned in order to meet the minimum requirements for applying the 'plans' theme?

  • A. A specific plan must be produced for managing agreed risk responses
  • B. The project manager must consider having more management stages
  • C. The defined tolerances must be aligned to the project board's risk attitude
  • D. A diagram showing the product interdependencies must be produced
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
themvp9
Highly Voted 2 years, 9 months ago
B should be correct 9.2 The more complex and risky a project, the more management stages that will be required (PRINCE2’s manage by stages principle)
upvoted 8 times
...
skillfulsatellite
Most Recent 4 days, 19 hours ago
Selected Answer: B
For a risky and complex project, PRINCE2 recommends breaking the project into more management stages. This provides the Project Board with more frequent decision points to monitor progress, review risks, and ensure continued business justification. By having shorter stages, risks are better managed, and corrective actions can be taken sooner if needed.
upvoted 1 times
...
fgtfgtet4r56y
1 year, 1 month ago
C. The defined tolerances must be aligned to the project board's risk attitude When planning a risky and complex project in order to meet the minimum requirements for applying the 'plans' theme in PRINCE2, it's essential to ensure that the defined tolerances are aligned with the project board's risk attitude. This means that the project's tolerance levels should be set in a way that is consistent with the project board's willingness to accept and manage risk. This alignment helps in risk management and ensures that the project is planned in a way that is compatible with the organization's risk appetite and the specific circumstances of the project.
upvoted 1 times
...
KANDUUR
2 years, 10 months ago
9.2 recommendation.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...