Exam PRINCE2-Practitioner topic 10 question 21 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 21
Topic #: 10
[All PRINCE2-Practitioner Edition 6 Questions]

The project is in stage 3. Zero time tolerance has been given for this stage. When checking progress, the project manager noticed that the checkpoint report from the external supplier of the 'e-learning course' is late. As work package progress information is missing, the project manager has decided to raise an exception report.
Is this an appropriate action, and why?

  • A. Yes, because an exception report should be used to request guidance on how this situation should be handled.
  • B. Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
  • C. No, because the project manager should check the operations and maintenance interfaces in the work package first.
  • D. No, because the team plan should be discussed with the supplier to check whether work will be completed on time.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ManikRoy
1 year, 3 months ago
Selected Answer: D
Rectified my previous answer. Option D is correct as the Project manager needs to discuss this with team manager.
upvoted 1 times
...
ManikRoy
1 year, 3 months ago
Selected Answer: A
The appropriate answer to the question is A, "Yes, because an exception report should be used to request guidance on how this situation should be handled." An exception report is a document that highlights any issues or concerns that may impact the project's success. It is used to notify the project board and seek guidance on how to handle the situation. B is NOT the correct answer as zero tolerance means product should be delivered on time not the checkpoint report. D is NOT the correct answer as Project manager is not supposed to check the team plan from a external supplier.
upvoted 1 times
...
ravi_aws
1 year, 3 months ago
A As there is zero time tolerance for this stage, the checkpoint report must be delivered on time. Therefore, the project manager should raise an exception report to request guidance on how this situation should be handled
upvoted 1 times
ravi_aws
1 year, 3 months ago
while option B is not entirely incorrect, option A is more comprehensive and accurately reflects the PRINCE2 methodology’s approach to handling such situations. It’s not just about enforcing deadlines, but also about managing exceptions and seeking guidance when tolerances are forecasted to be exceeded. So, option A is the most appropriate response in this scenario.
upvoted 1 times
...
...
Carpediempyy
1 year, 3 months ago
Selected Answer: A
Figure 15.5 shows the inputs to, and outputs from, this activity. PRINCE2 recommends the following actions: •In response to informal requests for advice and guidance: •seek advice from corporate, programme management or the customer if necessary •assist the project manager as required (this may include asking the project manager to produce an issue report and/or an exception report).
upvoted 1 times
...
KPBGBAP
1 year, 11 months ago
Selected Answer: D
D is correct - because "checkpoint report" is missing "Status is unknown"
upvoted 2 times
...
schris
2 years, 3 months ago
Correct answer should be A - page 150: "During execution of a stage plan, if any forecasts indicate that the management stage is likely to exceed the agreed management stage tolerances, then the deviation should be referred to the project board by the project manager in order to get a decision on corrective action. This would be done by raising an issue and an exception report."
upvoted 1 times
...
chancol
2 years, 9 months ago
I think the question is very confusing. It states that the checkpoint report is late, not that the product delivery is late. The project manager just did not receive information. This is not a situation to raise an exception report. I think D is the correct answer.
upvoted 2 times
...
anti8
3 years ago
I think B i correct. A.10.1
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago