Exam PRINCE2-Foundation topic 1 question 364 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 364
Topic #: 1
[All PRINCE2-Foundation Questions]

How should the 'managing product delivery' process be used?

  • A. As a way of obtaining project acceptance from the project board
  • B. As an alternative to using the PRINCE2 quality review technique
  • C. As an interface to third party suppliers that are not using PRINCE2
  • D. As a way to allow team managers to create their own work packages
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_124&showNav=true&expandNav=true

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
lucafranco
Highly Voted 2 years, 10 months ago
I think correct anwer is C. From 18.3: If the project uses external suppliers that are not using PRINCE2, managing product delivery provides a statement of the required interface between the team manager and the PRINCE2 method being used in the project by the project manager
upvoted 6 times
...
lferolm
Most Recent 1 year, 9 months ago
Selected Answer: C
Agree is C.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.