Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 364
Topic #: 1
[All PRINCE2-Foundation Questions]

How should the 'managing product delivery' process be used?

  • A. As a way of obtaining project acceptance from the project board
  • B. As an alternative to using the PRINCE2 quality review technique
  • C. As an interface to third party suppliers that are not using PRINCE2
  • D. As a way to allow team managers to create their own work packages
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_124&showNav=true&expandNav=true

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
lucafranco
Highly Voted 1 year, 7 months ago
I think correct anwer is C. From 18.3: If the project uses external suppliers that are not using PRINCE2, managing product delivery provides a statement of the required interface between the team manager and the PRINCE2 method being used in the project by the project manager
upvoted 6 times
...
Sam_femi
Most Recent 3 weeks ago
Selected Answer: C
The 'Managing Product Delivery' process ensures that the project team delivers the agreed-upon products to the project’s quality criteria, within time and cost constraints. It provides a clear framework for delivering products and managing the work packages assigned to the team. One of its roles is to manage the interface between the project and third-party suppliers or other external parties who may not be using PRINCE2. This ensures that all external parties understand the project’s requirements, expectations, and standards, even if they are not familiar with the PRINCE2 methodology.
upvoted 1 times
...
lferolm
6 months, 2 weeks ago
Selected Answer: C
Agree is C.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago