Which process plans the activities of the 'closing a project' process?

  • A. Closing a project
  • B. Managing a stage boundary
  • C. Directing a project
  • D. Starting up a project
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://www.greycampus.com/opencampus/prince-2-practitioner/activities-of-closing-a-project-process-in-prince2

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
themvp9
Highly Voted 2 years, 9 months ago
I would say A: The activities within the closing a project process are project-manageroriented and are to: prepare planned closure prepare premature closure hand over products evaluate the project recommend project closure.
upvoted 5 times
...
Examcollectorthanos
Most Recent 1 week, 5 days ago
B is correct. The other options are not correct because: A. Closing a project: This process executes the closure activities, not plans them. C. Directing a project: This process focuses on overall project direction and decision-making, not the detailed planning of closure activities. D. Starting up a project: This process sets up the initial project, not its closure.
upvoted 1 times
...
bes_i
4 months, 1 week ago
Selected Answer: B
B. Managing a Stage Boundary The 'Managing a Stage Boundary' process involves preparing for the end of a stage and planning for the next one, including the activities necessary for closing the project. This process ensures that all the necessary steps are taken to finalize and close the project properly, including addressing any outstanding issues and ensuring that all deliverables meet the required standards.
upvoted 1 times
...
Myname
1 year, 4 months ago
The correct answer is A. At the end of the last stage, there are no more no more products, hence no more stages to manage. The correct answer is therefore option A.
upvoted 1 times
...
AliSami
2 years, 7 months ago
B is the correct answer
upvoted 1 times
...
lucafranco
2 years, 11 months ago
I think that this is a tricky question. The correct answer its B 'Manage a stage boundry'. The question ask which process PLANS the activities about closing the project and not where those activity are executed.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...