exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 23 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 23
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is an objective of the 'closing a project' process?

  • A. To provide corporate management with an interface to the project
  • B. To ensure the project's delivery will be within set tolerances
  • C. To seek approval to replace the project or stage plan
  • D. To assess the benefits that have already been realized
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
lucafranco
Highly Voted 3 years ago
Correct answer shold be D: 20.2 assess any benefits that have already been realized and update the benefits management approach to include any post-project benefit reviews
upvoted 17 times
...
Tonderuzayi
Most Recent 2 months, 2 weeks ago
have someone used this dump for version 7?
upvoted 1 times
...
a2d1fd1
8 months, 2 weeks ago
Selected Answer: D
D is the correct answer not B
upvoted 2 times
...
AngeloC
11 months, 3 weeks ago
Selected Answer: D
An objective of the Closing a project is to assess the benefits already realized and plan review of benefits that will be realized after the project is complete (https://prince2.wiki/processes/closing-a-project/) The correct answer is D
upvoted 1 times
...
Adrienne
1 year, 3 months ago
Selected Answer: D
D - Assess the benefits already realized and plan review of benefits that will be realized after the project is complete
upvoted 2 times
...
mr_alok
1 year, 9 months ago
D is correct Not sure why the answer has not been corrected yet
upvoted 1 times
...
skshah47
1 year, 9 months ago
D is correct
upvoted 2 times
...
SGN63
1 year, 9 months ago
Selected Answer: D
D is the right answer
upvoted 2 times
...
renza
1 year, 10 months ago
Selected Answer: D
D is the right answer
upvoted 2 times
...
as055b
1 year, 10 months ago
I would say D - Assess the benefits already realized and plan review of benefits that will be realized after the project is complete.
upvoted 2 times
...
KeanoD
2 years, 4 months ago
Selected Answer: D
D is correct
upvoted 2 times
...
OridanDesta
2 years, 6 months ago
Selected Answer: D
D is correct
upvoted 2 times
...
Isabaut
2 years, 7 months ago
Selected Answer: D
D correct
upvoted 3 times
...
Annie7799666
2 years, 7 months ago
Answer is D. The objectives of the Closing a Project process are to: Verify user acceptance of the project’s products. Ensure that products can be supported after the project is disbanded. Review the performance of the project. This is done by comparing the project to the baselined documents. Assess the benefits already realized and plan review of benefits that will be realized after the project is complete. Address open issues and risks with a follow-up on action recommendations.
upvoted 3 times
...
jan_d
2 years, 8 months ago
Selected Answer: D
The provided reference does not justify B and it does not make sense logically either. D should be correct.
upvoted 3 times
...
hazrdz
2 years, 8 months ago
Selected Answer: D
Correct is D
upvoted 3 times
...
mazzantiemanuele
2 years, 9 months ago
Correct answer shold be D
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago