How is the 'tailor to suit the project' principle applied in an agile context?

  • A. By flexing what is produced to stay in control and deliver value
  • B. By emphasizing tolerances on what is being delivered
  • C. By using the Agilometer to assess the project environment
  • D. By fitting releases into planned management stages
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
KayBatah
1 year, 1 month ago
Selected Answer: C
7.3 Guidance on applying the PRINCE2 principles Table 7.1 Overview of the guidance when applying PRINCE2 principles in an agile context Tailor to suit the project environment PRINCE2 Agile incorporates an agile assessment tool (the Agilometer: see Chapter 24), which enables further specific tailoring by assessing the risks associated with the agile way of working with respect to the project environment (e.g. How engaged is the customer? How easy is communication?).
upvoted 2 times
...
Djtomip
1 year, 1 month ago
Selected Answer: C
In that case, for the application of the "tailor to suit the project" principle in the context of PRINCE2 Agile, the more precise choice is: C. By using the Agilometer to assess the project environment. This option directly references a tool within PRINCE2 Agile that helps evaluate the project's need for agility and guides the tailoring of the approach accordingly.
upvoted 2 times
...
Djtomip
1 year, 2 months ago
A. By flexing what is produced to stay in control and deliver value. In an Agile context, the "tailor to suit the project" principle is applied by flexing what is produced to stay in control and deliver value. This means that the Agile approach is tailored to the specific needs of the project, rather than trying to force a one-size-fits-all approach. The Agile Manifesto emphasizes the importance of responding to change and delivering working software frequently, which requires a flexible and adaptable approach. This means that the Agile team must be able to adjust their approach to suit the specific needs of the project and respond to changing requirements and priorities. By tailoring the Agile approach to the project, the team can stay in control of the project and ensure that they are delivering value to the customer. This may involve adjusting the Agile ceremonies, such as Sprint Planning or Daily Scrum, to better suit the needs of the project, or incorporating additional practices or tools to address specific project requirements.
upvoted 1 times
...
user0044
1 year, 9 months ago
for quality Prince2 training in Pakistan, visit this trainer’s website: https://www.javedpmp.com/prince2-certification-training.php
upvoted 1 times
...
alice07
1 year, 10 months ago
The correct answer is C as agreed with the comment below. A is "Focus on the Product" - by flexing what is delivered to make it easy to stay in control.
upvoted 2 times
...
AJ2021
2 years, 11 months ago
Correct Answer: C. By using the Agilometer to assess the project environment. Page 40 of official book v2018
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.