7.3 Guidance on applying the PRINCE2 principles
Table 7.1 Overview of the guidance when applying PRINCE2 principles in an agile context
Tailor to suit the project environment
PRINCE2 Agile incorporates an agile assessment tool (the Agilometer: see Chapter 24), which enables further specific tailoring by assessing the risks associated with the agile way of working with respect to the project environment (e.g. How engaged is the customer? How easy is communication?).
In that case, for the application of the "tailor to suit the project" principle in the context of PRINCE2 Agile, the more precise choice is:
C. By using the Agilometer to assess the project environment.
This option directly references a tool within PRINCE2 Agile that helps evaluate the project's need for agility and guides the tailoring of the approach accordingly.
A. By flexing what is produced to stay in control and deliver value.
In an Agile context, the "tailor to suit the project" principle is applied by flexing what is produced to stay in control and deliver value. This means that the Agile approach is tailored to the specific needs of the project, rather than trying to force a one-size-fits-all approach.
The Agile Manifesto emphasizes the importance of responding to change and delivering working software frequently, which requires a flexible and adaptable approach. This means that the Agile team must be able to adjust their approach to suit the specific needs of the project and respond to changing requirements and priorities.
By tailoring the Agile approach to the project, the team can stay in control of the project and ensure that they are delivering value to the customer. This may involve adjusting the Agile ceremonies, such as Sprint Planning or Daily Scrum, to better suit the needs of the project, or incorporating additional practices or tools to address specific project requirements.
The correct answer is C as agreed with the comment below. A is "Focus on the Product" - by flexing what is delivered to make it easy to stay in control.
Correct Answer: C. By using the Agilometer to assess the project environment. Page 40 of official book v2018
upvoted 4 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
KayBatah
1 year, 1 month agoDjtomip
1 year, 1 month agoDjtomip
1 year, 2 months agouser0044
1 year, 9 months agoalice07
1 year, 10 months agoAJ2021
2 years, 11 months ago