B. It can result in the early delivery of a minimum viable product
Explanation:
The target of 'accept that the customer doesn't need everything' in Agile methodologies focuses on delivering the most valuable and essential features first. By prioritizing the most critical requirements and acknowledging that not all initially identified features are necessary for the product's success, teams can deliver a minimum viable product (MVP) earlier. This approach allows the customer to start using the product sooner and provides valuable feedback for future iterations.
A. It gives confidence on the progress of the project: While it can contribute to overall project confidence, this statement does not directly capture the essence of the target.
C. It allows misunderstandings to be dealt with appropriately: This is more about communication and clarification rather than prioritizing and delivering essential features.
D. It is achieved by managing the culture of the team carefully: While managing team culture is important, it is not the primary focus of this target.
Which statement about the 'accept that the customer doesn't need everything' target is correct?
A. It gives confidence on the progress of the project
B. It can result in the early delivery of a minimum viable product
C. It allows misunderstandings to be dealt with appropriately
D. It is achieved by managing the culture of the team carefully
B. It can result in the early delivery of a minimum viable product.
The correct statement about the 'accept that the customer doesn't need everything' target is that it can result in the early delivery of a minimum viable product.
This target is a key principle of agile development, which recognizes that not all requirements are equal and that it is important to focus on delivering the features that will provide the most value to the customer. By accepting that the customer doesn't need everything, the team can focus on delivering the minimum viable product (MVP) as early as possible. This helps to ensure that the team is delivering value to the customer and can receive feedback that can be used to improve the product.
Agile is built upon the concept of “flexing” or “prioritizing” what is delivered to create value at the earliest point. This represents a significant change in how people think and act when working on a project. The project board needs to understand this to provide effective governance to the project
B has a bold sense in it.. If not everything is important to the user then what us the essence of delaying the project with useless requirements whose values isn't important to the overall product
Accept that the customer does not need everything .....Accepting the premise that not everything defined in the initial stages of a project must be delivered is wise. It inevitably turns out that many things do not add enough value to warrant delaying the project because of them.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
AJ2021
Highly Voted 2Â years, 11Â months agohusnus
Most Recent 6Â months, 1Â week agoKayBatah
1Â year, 1Â month agoDjtomip
1Â year, 2Â months agoDjtomip
1Â year, 2Â months agoczmshote
1Â year, 3Â months agoBrianMwasaru
2Â years, 4Â months agoJagmeet
2Â years, 6Â months ago