Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2 Agile Foundation All Questions

View all questions & answers for the PRINCE2 Agile Foundation exam

Exam PRINCE2 Agile Foundation topic 1 question 16 discussion

Actual exam question from PRINCE2's PRINCE2 Agile Foundation
Question #: 16
Topic #: 1
[All PRINCE2 Agile Foundation Questions]

What needs to happen when new detailed requirements are added to a timebox?

  • A. Requirements of a similar level of effort should be removed
  • B. More people should be added to the delivery team
  • C. The delivery milestones should be reviewed and re-planned
  • D. Formal change control should be applied
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
SD1978
1 year ago
Correct answer should be D
upvoted 1 times
...
Djtomip
1 year, 1 month ago
Selected Answer: C
If you can only choose one option, then the more appropriate choice would typically be: C. The delivery milestones should be reviewed and re-planned This option directly addresses the need to adjust the project plan and schedule to accommodate the new detailed requirements within the timebox. It is a standard practice in project management to review and re-plan when changes occur to ensure that the project remains on track. Option A (removing similar-level effort requirements) is a potential strategy within this re-planning process, but it doesn't encompass the entire process of assessing and adjusting the project plan, which is covered by option C.
upvoted 2 times
...
Gepro
1 year, 4 months ago
Selected Answer: A
A as per negative selection: B) The well-known "keep teams stable" doesn't allow me to choose B C) Time is fixed. D) Formal change control is not applied for detailed requirements as per PRINCE2 Agile
upvoted 3 times
...
darthhansie
1 year, 8 months ago
Selected Answer: A
If the new requirements cannot be accommodated within the existing timebox without compromising the delivery of other requirements, then it may be necessary to remove requirements of a similar level of effort in order to make room for the new requirements. This is often referred to as the "feature trade-off" approach.
upvoted 1 times
...
ptanmoyp
1 year, 9 months ago
Can be C...
upvoted 1 times
...
AJ2021
2 years, 11 months ago
A is correct, I'll take that first comment back, had a look into this deeper.
upvoted 1 times
...
AJ2021
2 years, 11 months ago
I think: D. Formal change control should be applied
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...