If you can only choose one option, then the more appropriate choice would typically be:
C. The delivery milestones should be reviewed and re-planned
This option directly addresses the need to adjust the project plan and schedule to accommodate the new detailed requirements within the timebox. It is a standard practice in project management to review and re-plan when changes occur to ensure that the project remains on track. Option A (removing similar-level effort requirements) is a potential strategy within this re-planning process, but it doesn't encompass the entire process of assessing and adjusting the project plan, which is covered by option C.
A as per negative selection:
B) The well-known "keep teams stable" doesn't allow me to choose B
C) Time is fixed.
D) Formal change control is not applied for detailed requirements as per PRINCE2 Agile
If the new requirements cannot be accommodated within the existing timebox without compromising the delivery of other requirements, then it may be necessary to remove requirements of a similar level of effort in order to make room for the new requirements. This is often referred to as the "feature trade-off" approach.
I think: D. Formal change control should be applied
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
SD1978
1 year agoDjtomip
1 year, 1 month agoGepro
1 year, 4 months agodarthhansie
1 year, 8 months agoptanmoyp
1 year, 9 months agoAJ2021
2 years, 11 months agoAJ2021
2 years, 11 months ago