Question #: 2
Topic #: 1
[All PRINCE2 Agile Foundation Questions]

Which is a key objective of running a workshop?

  • A. To make daily progress visible to the delivery team and key stakeholders
  • B. To encourage collaboration and create the defined outputs from the event
  • C. To communicate decisions to the wider stakeholder community
  • D. To make day-to-day decisions on behalf of the delivery team within a sprint
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_166&showNav=true&expandNav=true

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Sassou
1 year ago
Of course B
upvoted 1 times
...
AJ2021
2 years, 11 months ago
Agree B: Workshops are a very powerful tool. When run correctly they can create high-quality outputs in short spaces of time through motivated individuals collaborating and communicating effectively. This in turn creates clarity, consensus and ownership.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...