Question #: 209
Topic #: 1
[All PRINCE2-Foundation Questions]

In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?

  • A. Directing a project
  • B. Managing product delivery
  • C. Managing a stage boundary
  • D. Initiating a project
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.prince2.com/blog/the-7-principles-themes-and-processes-of-prince2/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Selded
2 years, 11 months ago
B is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other