B. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
This statement is NOT a purpose of the Initiating a Project process.
Here's why:
The Initiating a Project process is conducted after the project has been approved, not before. The purpose of this process is to set the groundwork for the project and provide the Project Board with the necessary information to give formal approval to proceed. The work to deliver the project's products is detailed in the Project Initiation Documentation (PID), which is developed during this process, but the purpose of Initiating a Project is not to understand the work beforehand—it is to formalize and ensure that the project can be successfully delivered.
The answer is D
The purpose of the initiating a project process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project product before committing to a significant spend.
The answer is D
These are key words for each process:
starting up a project: deciding whether the project is(viable and worthwhile)?
Initiating a project: establish (solid foundations) for the project.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
3578791
1 month, 2 weeks agoa2d1fd1
8 months, 2 weeks agomajoy010190
1 year, 2 months agoOmai
1 year, 9 months agorenza
1 year, 10 months agoArifNazin
1 year, 10 months agohazrdz
2 years, 4 months agomk_dyn365
3 years agoToni85
2 years, 8 months agoOridanDesta
2 years, 6 months ago