exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 37 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 37
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is NOT a purpose of the Initiating a Project process?

  • A. Enable a Project Board decision about the commitment of resources to a project
  • B. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
  • C. Establish solid foundations for a project
  • D. Enable the Project Board to decide whether it is worthwhile to initiate a project
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
3578791
1 month, 2 weeks ago
B. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved This statement is NOT a purpose of the Initiating a Project process. Here's why: The Initiating a Project process is conducted after the project has been approved, not before. The purpose of this process is to set the groundwork for the project and provide the Project Board with the necessary information to give formal approval to proceed. The work to deliver the project's products is detailed in the Project Initiation Documentation (PID), which is developed during this process, but the purpose of Initiating a Project is not to understand the work beforehand—it is to formalize and ensure that the project can be successfully delivered.
upvoted 1 times
...
a2d1fd1
8 months, 2 weeks ago
Selected Answer: D
D is not a purpose of the initiation process.
upvoted 1 times
...
majoy010190
1 year, 2 months ago
D is the answer. The statement includes the word “Initiate” not realize. Why do you suppose that the correct answer should be A ?
upvoted 1 times
...
Omai
1 year, 9 months ago
The answer is D The purpose of the initiating a project process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project product before committing to a significant spend.
upvoted 2 times
...
renza
1 year, 10 months ago
Selected Answer: D
The answer is D These are key words for each process: starting up a project: deciding whether the project is(viable and worthwhile)? Initiating a project: establish (solid foundations) for the project.
upvoted 3 times
...
ArifNazin
1 year, 10 months ago
Selected Answer: D
Cannot be A, as one of the objective of initiation stage is to allow PB to make decision on the resources.
upvoted 1 times
...
hazrdz
2 years, 4 months ago
Selected Answer: A
Answer should be A
upvoted 1 times
...
mk_dyn365
3 years ago
Answer Should be A. If anyone can confirm, will be grateful. TIA
upvoted 2 times
Toni85
2 years, 8 months ago
D is a purpose of 12. Start-up of a Proyect
upvoted 6 times
OridanDesta
2 years, 6 months ago
I agree to this statement
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago