4.3.2: The project manager is responsible for identifying and documenting the level of tailoring for the project. Tailoring affects how a project is managed and so it is documented as part of the PID, which is reviewed by the appropriate stakeholders and approved by the project board.
This question is misleading as there is difference between defining and approving. However the answer is chosen based on best fit as the other options are not correct.
A is correct
The project board is responsible for approving the tailoring approach. But it is the responsibility of the PM to identify and document the level of tailoring in the project
upvoted 4 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ebarb
Highly Voted 3 years agoomande
Most Recent 1 year, 1 month agoVJ80
1 year, 11 months agoChucky2
1 year, 12 months ago