Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 147 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 147
Topic #: 1
[All PRINCE2-Foundation Questions]

How is the tailoring approach defined for a project?

  • A. The project board approves the approach
  • B. The project board documents the approach
  • C. Project assurance approves the approach
  • D. Project assurance documents the approach
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ebarb
Highly Voted 3 years ago
ridiculous question
upvoted 8 times
...
omande
Most Recent 1 year, 1 month ago
4.3.2: The project manager is responsible for identifying and documenting the level of tailoring for the project. Tailoring affects how a project is managed and so it is documented as part of the PID, which is reviewed by the appropriate stakeholders and approved by the project board.
upvoted 2 times
...
VJ80
1 year, 11 months ago
This question is misleading as there is difference between defining and approving. However the answer is chosen based on best fit as the other options are not correct.
upvoted 2 times
...
Chucky2
1 year, 12 months ago
Selected Answer: A
A is correct The project board is responsible for approving the tailoring approach. But it is the responsibility of the PM to identify and document the level of tailoring in the project
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...