Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 13 question 4 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 4
Topic #: 13
[All PRINCE2-Practitioner Edition 6 Questions]

What products will be impacted by this change?

  • A. All of the project's products created so far.
  • B. Only those products created in the first three weeks of stage 3.
  • C. All of the project's products which relate to or include services provided by the Facilities Division.
  • D. No products would need to be changed but some will need to be removed from the project.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
A. All of the project's products created so far. This is because the MFH Quality Manager will administer the configuration management procedure for the Restructuring project, and this procedure must comply with the MFH document control process. Therefore, all of the project's products created so far will need to be reviewed and updated to comply with the new configuration management procedure. This includes any documents, plans, reports, or other project deliverables that have been created up to this point.
upvoted 1 times
...
watew
3 years, 1 month ago
Duplicate Question 12, Topic 7
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.