Having created the Issue Report and analyzed the impact of removing the Facilities Division from the scope of the Outsourcing project, the proposed option exceeds tolerance. \Nhat is the next action the Project Manager should consider?
A.
Create an Exception Report to inform the Project Board of the situation and the available options.
B.
Update the associated Configuration Item Records with details of the Issue Report that caused the change.
C.
Amend the Stage Plan for stage 3: remove all products related to the Facilities Division and add the activities required to deliver the new Government initiative.
D.
Create an Exception Plan to change all of the project's products to reflect the exclusion of services provided by the Facilities Division.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
watew
3 years, 1 month ago