Question #: 5
Topic #: 9
[All PRINCE2-Practitioner Edition 6 Questions]

Which other management product is created when the Business case is updated during Initiating a Project?

  • A. Post project review plan
  • B. Risk Register
  • C. Benefits Review plan
  • D. Issue Register
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
In PRINCE2, when the Business Case is updated during the Initiating a Project process, the Benefits Review Plan is also created. The purposes are: Business Case - To re-validate the reasons for doing the project Benefits Review Plan - To define how project benefits will be measured
upvoted 1 times
...
SantiagoAregentina
1 year, 2 months ago
Selected Answer: C
Ref Table 16.8
upvoted 1 times
...
GSD547
2 years, 7 months ago
Figure 16.9 (p209) shows that the Benefits Management Approach is Created and the same time the Detailed Business Case is created (so the original Business Case is updated to make it the Detailed one).
upvoted 3 times
...
timedout
3 years, 1 month ago
I think it should be "Update the benefits management approach" - Page 418 19.4.3
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...