In PRINCE2, when the Business Case is updated during the Initiating a Project process, the Benefits Review Plan is also created.
The purposes are:
Business Case - To re-validate the reasons for doing the project
Benefits Review Plan - To define how project benefits will be measured
Figure 16.9 (p209) shows that the Benefits Management Approach is Created and the same time the Detailed Business Case is created (so the original Business Case is updated to make it the Detailed one).
I think it should be "Update the benefits management approach" - Page 418 19.4.3
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ravi_aws
1 year, 1 month agoSantiagoAregentina
1 year, 2 months agoGSD547
2 years, 7 months agotimedout
3 years, 1 month ago