Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 108 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 108
Topic #: 1
[All PRINCE2-Foundation Questions]

Which statement about the quality review technique is FALSE?

  • A. It enables a check to be made on a product's fitness for purpose
  • B. It defines the quality responsibilities of the project team
  • C. It supports the management of future changes by providing a baseline for a product
  • D. It is used to gain wider acceptance of a product by involving key interested parties
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
omande
1 year, 1 month ago
Selected Answer: B
8.4.1: The objectives of a PRINCE2 quality review are to: ● assess the conformity of a product against the quality criteria documented in the product description ● involve key interested parties in checking the product’s quality and in promoting wider acceptance of the product. ● provide confirmation that the product is complete and ready for approval. ● baseline the product for future change control.
upvoted 2 times
...
peppe
3 years, 1 month ago
responsibilities are in QM approach!
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...