When should the Project Board refer to corporate or programme management for a decision?

  • A. The stage requires resources
  • B. It is forecast that project level tolerance will be exceeded
  • C. The Senior Supplier or Senior User needs to be changed
  • D. Any request for change needs to be approved
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
renza
1 year, 9 months ago
Selected Answer: B
- setting tolerances • Corporate management: set project tolerances • project board: set stage tolerances • project manager agrees with team manager: set workpackages tolerances So any exceeding of these tolerances requires approval from these authorities. B is the right answer since the project tolerances is the Corporate management responsibility
upvoted 3 times
...
peppe
3 years, 1 month ago
B is correct
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.