Which process is triggered towards the end of the final stage when all the assigned work has been completed?

  • A. Managing a Stage Boundary
  • B. Managing Product Delivery
  • C. Closing a Project
  • D. Controlling a Stage
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Laserboy
3 months, 3 weeks ago
The Closing a Project process is triggered towards the end of the final stage when all assigned work has been completed. This process involves finalizing all project activities, ensuring that all products have been delivered and accepted, and preparing for the formal closure of the project.
upvoted 1 times
...
Firey
1 year, 4 months ago
At the end of the last stage, the Closing a Project process will be invoked and therefore, the Project Manager will start to prepare the project for closure.
upvoted 1 times
...
peppe
3 years, 1 month ago
I believe is C: "received completed work"
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...