Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 29 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 29
Topic #: 1
[All PRINCE2-Foundation Questions]

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

  • A. Product Description
  • B. Team Plan
  • C. Work Package
  • D. Stage Plan
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
peppe
3 years, 1 month ago
C is correct the words " work to be done " are crucials
upvoted 3 times
...
peppe
3 years, 1 month ago
CORRECT :"The team manager has control for a work package, but only within the work package tolerances agreed with the project manager. During execution of the work package, if any forecasts indicate that it is likely that the agreed tolerances will be exceeded, then the deviation should be referred to the project manager by the team manager in order to get a decision on corrective action. This would be done by raising an issue.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...