CORRECT :"The team manager has control for a work package, but only within the work package tolerances agreed with the project manager. During execution of the work package, if any forecasts indicate that it is likely that the
agreed tolerances will be exceeded, then the deviation should be referred to the project manager by the team manager in order to get a decision on corrective action. This would be done by raising an issue.
upvoted 2 times
...