Question #: 4
Topic #: 4
[All PRINCE2-Practitioner Edition 6 Questions]

In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator:

  • A. Project manager
  • B. Project support
  • C. Team Manager
  • D. Project Assurance
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ManikRoy
1 year, 2 months ago
Selected Answer: B
Page 83, Project Support responsibilities.
upvoted 1 times
...
georgio1974
1 year, 3 months ago
Selected Answer: B
i would agree that it is B but it is not clear from any point that project support should provide administration support on pages 90-92 in new edition 2023
upvoted 1 times
...
PieroBe
1 year, 4 months ago
Selected Answer: B
Project Support, refer to 8.4.3.
upvoted 1 times
...
matters
3 years, 1 month ago
Refer to the Project Support responsibilities in Table 8.1 of the manual
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...