Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 141 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 141
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is an objective of the Starting up a Project process?

  • A. Identify who will be responsible for creating the Project Plan
  • B. Agree how the project will be monitored and controlled after initiation
  • C. Authorize the Project Manager to proceed with the initiation stage
  • D. Agree how issues and changes will be identified, assessed and controlled
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Chucky2
Highly Voted 1 year, 12 months ago
Selected Answer: A
A is correct The objective of starting up a project process is to ensure that there is a business justification for initiating the project. Sufficient information is available to define and confirm the scope of the project. The various ways that a project can be delivered are evaluated and a project approach is selected. Individuals are appointed who will undertake the work required in project initiation and all will take significant project management roles in the project.
upvoted 5 times
...
dandandu1986
Most Recent 1 year, 4 months ago
C. 14.2 individuals are appointed who will undertake the work required in project initiation and/or will take significant project management roles in the project
upvoted 1 times
...
MrMooMooBee
1 year, 10 months ago
Authorisation of the initiation stages is Directing a Project so C isn't correct.
upvoted 1 times
...
Risto83
1 year, 11 months ago
A "Authorize" is in directing a project.
upvoted 1 times
...
jj0097
2 years, 4 months ago
Selected Answer: C
C is good
upvoted 1 times
...
peppe
3 years, 1 month ago
The project plan is created during the initiating a project process and updated towards the end of each management stage during the managing a stage boundary process.
upvoted 3 times
...
peppe
3 years, 1 month ago
i would say C
upvoted 2 times
...
kal5
3 years, 1 month ago
Referens for this answer appriciated
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel