A is correct
The objective of starting up a project process is to ensure that there is a business justification for initiating the project. Sufficient information is available to define and confirm the scope of the project. The various ways that a project can be delivered are evaluated and a project approach is selected. Individuals are appointed who will undertake the work required in project initiation and all will take significant project management roles in the project.
C.
14.2 individuals are appointed who will undertake the work required in project initiation and/or will take significant project management roles in the project
The project plan is created during the initiating a project process and updated towards the end of each management stage during the managing a stage boundary process.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Chucky2
Highly Voted 1 year, 12 months agodandandu1986
Most Recent 1 year, 4 months agoMrMooMooBee
1 year, 10 months agoRisto83
1 year, 11 months agojj0097
2 years, 4 months agopeppe
3 years, 1 month agopeppe
3 years, 1 month agokal5
3 years, 1 month ago