Clearly C as it generates a conflict of interests between who is responsible of products deploy (Team Manager) and who is responsible of process to deploy products soundness (Project Assurance).
7.2.10 Combining roles - The executive and project manager roles cannot be combined, the project board should not assign any project assurance roles to the project manager, team manager or project support.
upvoted 2 times
...