Question #: 1
Topic #: 3
[All PRINCE2-Practitioner Edition 6 Questions]

Which of the following is False?
A Successful project management team should.

  • A. Have business, user and supplier stakeholder representation
  • B. Never be reviewed as members should stay with the team for the duration
  • C. Ensure appropriate governance by defining responsibilities for directing, managing and delivering the project and clearly defining accountability at all levels
  • D. Have an effective strategy to manage communication flows to and from stakeholders
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
schris
Highly Voted 2 years, 1 month ago
B is CORRECT (it is the only answer which is false). Answer A is not false, according to 7.1. (beginning of page 60) successful project management team should have all three stakeholders representation :)
upvoted 6 times
...
lucafranco
Most Recent 2 years, 10 months ago
Therefore, all three stakeholder interests need to be represented effectively in the project management team; two out of three is not enough
upvoted 2 times
...
timedout
3 years, 2 months ago
A is correct, see 7.1
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...