Question #: 53
Topic #: 1
[All PRINCE2-Foundation Questions]

Which does the Executive need to ensure is in place before the project is initiated?

  • A. All Work Packages are authorized
  • B. An understanding of how the project will contribute to corporate objectives
  • C. The Project Plan has been approved
  • D. The Project Initiation Documentation is complete
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Anneru
2 months, 2 weeks ago
Selected Answer: B
The Executive must ensure that the project's purpose and strategic alignment are clear. This is a key part of ensuring the project's justification, as outlined in the Business Case.
upvoted 1 times
...
matters
5 months, 2 weeks ago
The Project Board has to "Verify that the outline business case demonstrates a viable project." Ref 15.4.1 authorize Initiation.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago