Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 44 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 44
Topic #: 1
[All PRINCE2-Foundation Questions]

What process aims to ensure accurate progress information is provided to the Project Manager?

  • A. Starting up a Project
  • B. Managing a Stage Boundary
  • C. Managing Product Delivery
  • D. Directing a Project
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
6 days, 20 hours ago
The correct answer is C. Managing Product Delivery. Here's why: Managing Product Delivery: This process focuses on the interaction between the project manager and the team manager(s) who are responsible for creating the project's products. It's about controlling the work and ensuring that products are delivered to the required standards.
upvoted 1 times
...
matters
3 years, 2 months ago
C is correct. Refer to 18.2 Objective #4
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...