D
The objectives of the Directing a Project process are to provide authority (to make a decision)
To initiate the project (allow the Initiating a Project process to start).
To deliver the project’s products (start the delivery stages).
B. Initiating a Project
In PRINCE2, the Initiating a Project process is where the authorization to deliver the project's products is given. This is when the project board formally authorizes the project and its initiation, confirming that the project has a solid foundation to proceed, and it includes the creation of the Project Initiation Documentation (PID), which outlines the project's objectives, scope, risks, and plans.
In the directing a project process, authorisation is given to manage a project, to proceed continuously, and provide ad hoc direction when needed. The activities of directing a Project process include the following: Authorise initiation. Authorise the project.
In the Activity "Authorize the Project', the Project Board decides to allow the proceed.
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
skillfulsatellite
4 days, 2 hours ago3578791
1 week, 4 days agoFirey
1 year, 4 months agomatters
3 years, 2 months ago