Question #: 25
Topic #: 1
[All PRINCE2-Foundation Questions]

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

  • A. Directing a Project
  • B. Managing a Stage Boundary
  • C. Controlling a Stage
  • D. Starting up a Project
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
peppe
3 years, 1 month ago
C is correct
upvoted 2 times
...
S4L4LMF
3 years, 3 months ago
17.2 Objective: The objective of the controlling a stage process is to ensure that: attention is focused on delivery of the management stage’s products. Any movement away from the direction and products agreed at the start of the management stage is monitored to avoid uncontrolled change and loss of focus
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...