MANAGING A STAGE BOUNDARY -
The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process.
Which action should the project manager undertake as part of the 'update the business case' activity?

  • A. Identify the dependencies between the activities required to run the 'delivered pilot courses' during stage 4.
  • B. Revise the overall plan and resources to complete the project, based on actuals from the stage 3 plan.
  • C. Review the performance of the external suppliers who worked on delivery of the 'e-learning course' during stage 3.
  • D. Re-plan when the number of learners using the pilot course, and their increased knowledge, will be measured during stage 4.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Chivasa
1 year, 1 month ago
Selected Answer: B
19.4.3 page 252
upvoted 2 times
...
ManikRoy
1 year, 1 month ago
Selected Answer: D
Option D seems to be the correct answer to me as this is updating business case with actions for benefit management review of next stage. Ref 19.4.3 in the manual , Examine and Review last point -- whether any benefits reviews are required in the next management stage
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
B. Revise the overall plan and resources to complete the project, based on actuals from the stage 3 plan. Updating the business case involves ensuring that the project remains viable and justifiable given the current situation. This includes revising the overall plan and resource requirements based on the actual progress and costs incurred during the previous stage (in this case, stage 3). This revision helps ensure that the project is on track and that the business case remains valid for continuing with the project.
upvoted 3 times
...
PieroBe
1 year, 4 months ago
To my opinion it is D. According to Ref. 19.4.3: "Update the benefit management approach with the results from any benefit management actions undertaken during the (completed) management stage" as we can assume the fact pilot courses have been planned during closing stage 3 can trigger when the number of learners can be measured.
upvoted 2 times
...
windy1
2 years, 11 months ago
I think it is B - based on 19.4.3
upvoted 3 times
...
lovelifeysl_2021
3 years ago
I think it is C, what do you think?
upvoted 1 times
...
pollon
3 years, 3 months ago
D - Update the business case Ref 19.4.3 - exam and review: whether any benefits reviews are required in the next management stage
upvoted 3 times
timedout
3 years, 2 months ago
Can you explain the rational behind D please Pollon? How does this relate to "Examine & Review" Thanks
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...