Question #: 8
Topic #: 25
[All PRINCE2-Practitioner Edition 6 Questions]

The service level agreement contains a number of technical terms that are missing from its glossary of terms.

  • A. Obtain agreement from the Director of Facilities Division to add these into the glossary of terms within the remaining +2 days tolerance.
  • B. Raise an issue (off-specification).
  • C. Raise an issue (request for change).
  • D. No action required.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Terry007
9 months, 3 weeks ago
In my opinion, I would go for option B if the technical terms were misspelt, however the technical terms were missing altogether therefore it would be option C, requestion for Change.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
This is because the service level agreement is a product that should meet the quality criteria defined in its Product Description. If the glossary of terms is incomplete or inaccurate, it means that the product does not conform to its specification and therefore it is an off-specification. According to PRINCE2, an off-specification is a type of issue that should be recorded and handled through the issue and change control procedure. The other options are not appropriate because they either do not address the problem of the missing terms, or they involve the wrong roles or processes.
upvoted 1 times
ravi_aws
1 year, 1 month ago
B is right
upvoted 1 times
...
...
pollon
3 years, 3 months ago
Why is it A not C?
upvoted 1 times
timedout
3 years ago
I think its because they are "missing" it will not be a change, as it was previously planned.
upvoted 1 times
...
timedout
3 years ago
Also I dont think this is classed as an off-specification just yet as the product can at this stage be delivered as planned if more time is given.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...