Which is a task of product-based planning?

  • A. Identify activities and dependencies
  • B. Write the Project Product Description
  • C. Prepare the Work Packages
  • D. Produce Product Status Accounts
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
KeanoD
2 years, 3 months ago
Selected Answer: B
PRINCE2 uses the technique Product-Based planning to identify and analyze the planned products. The four steps in Product-Based Planning are: 1. Writing the Project Product Description 2. Creating the product breakdown structure 3. Writing the Product Description 4. Creating the Product Flow Diagram
upvoted 4 times
...
Goseu
2 years, 11 months ago
its B , A is part of plans steps not pbp
upvoted 3 times
...
Sala_
3 years ago
B is correct Source: https://prince2.wiki/theme/plans/ PRINCE2 uses the technique Product-Based planning to identify and analyse the planned products. The four steps in Product-Based Planning are: Writing the Project Product Description: Describing the main product during the Starting up a Project process. Creating the product breakdown structure: Listing all products that need to be created. Writing the Product Description: Done for required products. Creating the Product Flow Diagram: Shows product flow and interdependencies.
upvoted 3 times
...
peppe
3 years, 1 month ago
A is correct
upvoted 1 times
...
consta
3 years, 4 months ago
Should be A. PRINCE2® recommends the following steps for product‐based planning: • Designing a plan; *Defining and analysing the products; Identifying activities and dependencies; Preparing estimates; Preparing a schedule; Documenting a plan; Analysing risks to a plan.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...