PRINCE2 uses the technique Product-Based planning to identify and analyze the planned products. The four steps in Product-Based Planning are:
1. Writing the Project Product Description
2. Creating the product breakdown structure
3. Writing the Product Description
4. Creating the Product Flow Diagram
B is correct
Source: https://prince2.wiki/theme/plans/
PRINCE2 uses the technique Product-Based planning to identify and analyse the planned products. The four steps in Product-Based Planning are:
Writing the Project Product Description: Describing the main product during the Starting up a Project process.
Creating the product breakdown structure: Listing all products that need to be created.
Writing the Product Description: Done for required products.
Creating the Product Flow Diagram: Shows product flow and interdependencies.
Should be A.
PRINCE2® recommends the following steps for product‐based planning:
• Designing a plan; *Defining and analysing the products; Identifying activities and dependencies; Preparing estimates; Preparing a schedule; Documenting a plan; Analysing risks to a plan.
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
KeanoD
2 years, 3 months agoGoseu
2 years, 11 months agoSala_
3 years agopeppe
3 years, 1 month agoconsta
3 years, 4 months ago