Which statement about stages is true?

  • A. Management stages should be of the same duration
  • B. The use of technical stages is mandatory
  • C. The use of management stages is mandatory
  • D. Management stages are driven by specialist teams
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nugi
Highly Voted 3 years, 4 months ago
In PRINCE2, a project must have at least two management stages: ● an initiation stage ● at least one further management stage. The more complex and risky a project is, the more management stages will be required.
upvoted 6 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...