When might the 'controlling a stage' process be used?

  • A. During the 'closing a project' process
  • B. During the 'directing a project' process
  • C. During the 'initiating a project' process
  • D. During the 'starting a project' process
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 5 days ago
Conflicted, chatGPT & Gemini giving diffrent answers.
upvoted 1 times
...
gauthier59
2 weeks, 1 day ago
I would say C is correct "The Controlling a Stage Process may be used during the Initiation Stage, especially for large or complex projects".
upvoted 1 times
...
fgtfgtet4r56y
1 year, 1 month ago
B. During the 'directing a project' process The "controlling a stage" process in PRINCE2 is used during the "directing a project" process. The purpose of the "controlling a stage" process is to monitor and control the work of a stage to ensure that it progresses according to the stage plan and objectives. The project manager, under the direction of the project board (directing a project), uses this process to manage the activities within a stage effectively.
upvoted 2 times
...
Myname
1 year, 4 months ago
Closing a project is not a management stage. Initiation of a project is a management stage in Prince2 framework. For large and complex projects, Controlling a stage' process is used during 'Initiating a stage'. I think the correct answer is therefore Option C
upvoted 1 times
...
KANDUUR
2 years, 10 months ago
If you check Figure 13.2 then it gives an answer: the question is wrong. It can be used in Initiation and closure too.
upvoted 2 times
...
p_sarkar
2 years, 11 months ago
Correct answer is C. Section 17.3: The Controlling a Stage Process may be used during the Initiation Stage, especially for large or complex projects.
upvoted 2 times
...
Martin77
3 years, 6 months ago
For this question - either the question is given wrong, or the answer is wrong. If the question is given correctly, then my answer would be during Directing A Project Process as : Reference Prince 2 - 17.3 This process will be used for each delivery stage of a project. Starting up a closing a project process, starting up a project process and initiating a project process are not exactly delivery processes to my understanding, so I would go with B. During the "Directing a project process" but I am not completely sure. Please provide some input
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...