Which TWO create desired outcomes?
1. Business changes
2. Project outputs
3. Benefits
4. Strategic objectives

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
skillfulsatellite
1 month, 1 week ago
Selected Answer: B
The two that create desired outcomes are: 2. Project outputs 3. Benefits
upvoted 1 times
...
Examcollectorthanos
1 month, 2 weeks ago
B is correct; Why the other options are incorrect: A. 1 and 2: While business changes (Option 1) are part of the broader organizational goals, the direct outcomes of a project are typically the outputs and the benefits. Business changes are influenced by the outputs and benefits but are not themselves direct outcomes. C. 3 and 4: Strategic objectives (Option 4) are the broader goals of an organization, which the project aims to support. However, the benefits are the more direct desired outcomes, and strategic objectives represent the high-level goals rather than specific outcomes created by the project. D. 1 and 4: Business changes (Option 1) and strategic objectives (Option 4) are part of the broader context but are not the direct outcomes created by a project. The actual outcomes come from the project outputs and the benefits.
upvoted 1 times
...
p_sarkar
3 years ago
A is correct. See Figure 6.1: Relationship between Outputs, Outcomes and Benefits.
upvoted 4 times
KANDUUR
2 years, 11 months ago
Project outputs enable Business change that creates Desired Outcomes. Figure 6.1 thank you p_sarkar !
upvoted 1 times
...
...
peppe
3 years, 2 months ago
A is correct
upvoted 1 times
...
waleed2030
3 years, 5 months ago
Project outputs - 100% correct (page 294, pirnce2 book page308) Answer will be A or B
upvoted 1 times
...
Martin77
3 years, 7 months ago
B is correct. 2. Project outputs 3. Benefits Reference Prince2 guide - A.2.2 Expected benefits These result from the desired outcomes to be achieved through the use of the project outputs. The benefits are expressed in measurable terms against the situation as it exists prior to the project.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago