Which type of issue should be raised if a quality review finds that a product does not meet the criteria in the product description?

  • A. A request for change
  • B. An off-specification
  • C. A problem
  • D. A concern
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
https://www.prince2primer.com/prince2-2017-quality-check/

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Martin77
Highly Voted 3 years, 6 months ago
This is wrong. I think the correct answer is B. off-specification according to the definitions in the Prince2 manual. off-specification (matches the question) Something that should be provided by the project, but currently is not (or is forecast not to be). It might be a missing product or a product not meeting its specifications. It is one type of issue. request for change A proposal for a change to a baseline. It is a type of issue. problem A type of issue (other than a request for change or off-specification) that the project manager needs to resolve or escalate. Also known as a concern.
upvoted 8 times
...
Examcollectorthanos
Most Recent 1 week, 5 days ago
B; The other options are not the most appropriate in this context: A. A request for change: This is used when a change to the product is desired, not when a product fails to meet existing criteria. C. A problem: While a problem might be the cause of the off-specification, the off-specification itself is the formal issue. D. A concern: This is a less formal term and doesn't trigger the same level of control and management as an off-specification. In summary: When a quality review finds that a product doesn't meet its defined criteria, an off-specification should be raised to formally record the issue and trigger the appropriate corrective actions.
upvoted 1 times
...
Ppp333
1 year, 2 months ago
Selected Answer: B
A.8.2 Off-specifications Listing any missing products or products that do not meet the original requirements, and confirmation of any concessions granted
upvoted 1 times
...
jj0097
2 years, 4 months ago
Selected Answer: B
B is good
upvoted 1 times
...
AliSami
2 years, 7 months ago
B is the correct answer
upvoted 2 times
...
Nugi
3 years, 4 months ago
Definitively the answer is B. Reference: Off-Specification is something that should be provided by the project, but currently is not (or is forecast not to be). It might be a missing product or a product not meeting its specifications.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...