Exam PRINCE2-Foundation topic 1 question 316 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 316
Topic #: 1
[All PRINCE2-Foundation Questions]

According to the 'tailor to suit the project' principle, what is the basis for effective project management?

  • A. That the appropriate number and type of meetings are held
  • B. That the project is divided into an appropriate number of stages
  • C. That the appropriate information is provided to make decisions
  • D. That the right people are involved in appropriate roles
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference:
https://prince2.wiki/principles/tailor-to-suit-the-project-environment/
Community vote distribution
C (100%)

Comments

Chosen Answer:
This is a voting comment. You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Martin77
Highly Voted 3 years, 10 months ago
This is wrong. C is correct. Reference Prince2 guide - 3.7 - When tailoring PRINCE2, it is important to remember that effective project management requires information (not necessarily documents) and decisions (not necessarily meetings).
upvoted 8 times
...
ArisL
Most Recent 1 week ago
Selected Answer: C
The correct answer is C. "When tailoring PRINCE2, it is important to remember that effective project management requires information (but not necessarily documents) and decisions (but not necessarily meetings)." Paragraph 2.7 of the book
upvoted 1 times
...
Examcollectorthanos
4 months, 3 weeks ago
I keep learning wrong answers, please change. ITs muscle memory
upvoted 1 times
...
Examcollectorthanos
4 months, 3 weeks ago
C is correct PLEASE CHANGE; A. That the appropriate number and type of meetings are held: While important, this is a part of tailoring communication, not the core basis for effective project management. B. That the project is divided into an appropriate number of stages: This is related to the "manage by stages" principle. D. That the right people are involved in appropriate roles: This is related to the "defined roles and responsibilities" principle.
upvoted 1 times
...
jj0097
2 years, 9 months ago
D is correct
upvoted 1 times
...
AliSami
2 years, 11 months ago
C is the correct answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
AIF-C01
Cape Town, 1 minute ago