This is wrong. C is correct. Reference Prince2 guide - 3.7 - When tailoring PRINCE2, it is important to remember that effective project management requires information (not necessarily documents) and decisions (not necessarily meetings).
The correct answer is C.
"When tailoring PRINCE2, it is important to remember that effective project management requires information (but not necessarily documents) and decisions (but not necessarily meetings)." Paragraph 2.7 of the book
C is correct PLEASE CHANGE;
A. That the appropriate number and type of meetings are held: While important, this is a part of tailoring communication, not the core basis for effective project management.
B. That the project is divided into an appropriate number of stages: This is related to the "manage by stages" principle.
D. That the right people are involved in appropriate roles: This is related to the "defined roles and responsibilities" principle.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Martin77
Highly Voted 3 years, 10 months agoArisL
Most Recent 1 week agoExamcollectorthanos
4 months, 3 weeks agoExamcollectorthanos
4 months, 3 weeks agojj0097
2 years, 9 months agoAliSami
2 years, 11 months ago