Correct answer is A.
See section "7.2.1.6 Change Authority" from PRINCE2 manual:
"The project manager and/or the people with delegated project assurance responsibilities may act as the change authority. Refer to Chapter 11 for more information on change."
Correct = A;
Why other options are not suitable:
B. Team manager: Team managers are responsible for managing the work of their team and delivering products, not for making decisions about changes to the project scope or plan.
C. Project support: Project support provides administrative assistance and does not have the authority to approve changes.
D. Team member: Team members are responsible for carrying out the work assigned to them and do not have the authority to approve changes.
In summary: While the project board ultimately holds the responsibility for change control, they can delegate the change authority to project assurance or another appropriate person or group to streamline the process and ensure efficient decision-making.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
theotenis
Highly Voted 3 years, 6 months agoExamcollectorthanos
Most Recent 1 week, 5 days agoExamcollectorthanos
1 week, 5 days agoMartin77
3 years, 6 months ago