Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 335 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 335
Topic #: 1
[All PRINCE2-Foundation Questions]

Which role can act as the change authority?

  • A. Project assurance
  • B. Team manager
  • C. Project support
  • D. Team member
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://yourprojectmanager.com.au/roles-change-authority-project-support-prince2-projects/

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
theotenis
Highly Voted 3 years, 6 months ago
Correct answer is A. See section "7.2.1.6 Change Authority" from PRINCE2 manual: "The project manager and/or the people with delegated project assurance responsibilities may act as the change authority. Refer to Chapter 11 for more information on change."
upvoted 6 times
...
Examcollectorthanos
Most Recent 1 week, 5 days ago
Please change this answer selected to A.
upvoted 1 times
...
Examcollectorthanos
1 week, 5 days ago
Correct = A; Why other options are not suitable: B. Team manager: Team managers are responsible for managing the work of their team and delivering products, not for making decisions about changes to the project scope or plan. C. Project support: Project support provides administrative assistance and does not have the authority to approve changes. D. Team member: Team members are responsible for carrying out the work assigned to them and do not have the authority to approve changes. In summary: While the project board ultimately holds the responsibility for change control, they can delegate the change authority to project assurance or another appropriate person or group to streamline the process and ensure efficient decision-making.
upvoted 1 times
...
Martin77
3 years, 6 months ago
I agree, A is correct
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...