A is correct; Why other options are not suitable:
B. Senior supplier: This role focuses on ensuring the supplier's contribution meets the project's needs.
C. Executive: This role has overall responsibility for the project and cannot be combined with any other project management team role.
D. Project manager: This role is responsible for day-to-day management and cannot be combined with any other project management team role.
A. Project Support
Project Support can be combined with the Business Assurance role, as both roles involve aspects of ensuring the project meets its requirements and delivers value. Business Assurance focuses on ensuring that the project is aligned with business needs and provides assurance that the project is adhering to required standards. Project Support can take on additional responsibilities related to assurance activities, including maintaining documentation and supporting compliance with project standards
Correct answer is C.
From the URL provided in the answer: "An important responsibility of the PRINCE2 project board is project assurance. This is part of the PRINCE2 project management team, and consists of three roles, business assurance, user assurance, and supplier assurance. "
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
skillfulsatellite
4 days, 20 hours agoExamcollectorthanos
1 week, 5 days agobes_i
4 months agoisuweera
1 year, 8 months agojj0097
2 years, 4 months agoMo1977
2 years, 4 months agoAliSami
2 years, 7 months agoMartin77
3 years, 6 months agotheotenis
3 years, 6 months ago