Identify the missing words in the following sentence. If approved, an exception plan will replace the [?] and show the actions required to recover from the efficient of a tolerance deviation.
C = correct; The other options are incorrect because:
A. benefits management approach: This outlines how benefits will be realized and is not directly related to managing tolerances.
B. project brief: This is the initial document that triggers the project and is not replaced by an exception plan.
D. team plan: Team plans are created by the project manager to manage work packages within a stage and are not replaced by exception plans.
This is wrong! It should be C. stage plan:
https://prince2.wiki/theme/plans/ reference from this link: Exception Plans can be used to replace Stage Plans and Project Plans, but not Team Plans.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week, 5 days agoEl_Cabron
1 year, 3 months agokuku1789
2 years, 1 month agojj0097
2 years, 4 months agohamed246
3 years, 4 months agoMartin77
3 years, 6 months ago