Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 5
Topic #: 10
[All PRINCE2-Practitioner Edition 6 Questions]

During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?

  • A. Team Plan
  • B. Checkpoint Report
  • C. Quality Register
  • D. Configuration Item Record
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
timedout
3 years, 1 month ago
Quality Register - 8.2 (page 152)
upvoted 3 times
...
WikiVicks
3 years, 6 months ago
I think B is more appropriate. A.4.2 states 'quality management activities carried out during the period'
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...