A) False - Technical stages can occur sequentially or in parallel.
B) False - Technical stages relate to the project lifecycle and work content, not management decision points.
C) True - It is common for technical stages to happen concurrently due to dependencies in the work flow.
D) False - Technical stages don't define resource/authority commitments - that is done at management stages in PRINCE2.
Know I'm pretty sure delivery steps = technical stages, thus referring to 9.3.1.1 we see that "Delivery steps often overlap...". Also, all the other are clearly falses.
This is possibly a question from the earlier versions of the exam. No mention is made of 'Technical Stages' in the 2017 Version 6 but the Technical stages correspond to the discussion on Delivery steps in the Plans Chapter ( #9) in the 2017 Version 6
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.