Exam PRINCE2-Practitioner topic 7 question 5 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 5
Topic #: 7
[All PRINCE2-Practitioner Edition 6 Questions]

When examining a project issue, which three aspects should be considered?
1. Performance targets
2. Business Case
3. Resources
4. Risk

  • A. 1, 3, 4
  • B. 2, 3, 4
  • C. 1, 2, 4
  • D. 1, 2, 3
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
pollon
Highly Voted 3 years, 3 months ago
Answer C is correct, see pg 144 of the manual - Impact analysis of an issue should consider: project performance targets, business case, dependent products produced by project, project risk profile
upvoted 8 times
...
ravi_aws
Most Recent 1 year, 1 month ago
C When examining a project issue in PRINCE2, the three aspects that should be considered are: Business Case Risk Performance targets
upvoted 1 times
...
SantiagoAregentina
1 year, 2 months ago
Selected Answer: C
Ref 11.4.2
upvoted 1 times
...
WikiVicks
3 years, 6 months ago
Incorrect answer. An issue is when something has already occurred. Risk is something that hasn't occurred yet and might occur ( not certain). So C cannot be correct. More likely D is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...