Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?

  • A. Project Assurance
  • B. Project Manager
  • C. Corporate or Programme Management
  • D. Project Support
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
WikiVicks
Highly Voted 3 years, 6 months ago
A Project Assurance -is the most logical answer. It's the Project Assurance's responsibility to ensure all standards are met including Communications Management Approach ( in the 2017 , Edition 6)
upvoted 5 times
...
matters
Most Recent 3 years, 1 month ago
Refer to Table 7.1 in the 6th edition manual
upvoted 2 times
georgio1974
1 year, 3 months ago
table 7.2,3 page 68 answer D project assurance
upvoted 1 times
georgio1974
1 year, 3 months ago
sorry A
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.