Question #: 2
Topic #: 10
[All PRINCE2-Practitioner Edition 6 Questions]

Which management product do the Project Board use to decide whether to authorize initiation?

  • A. Project Brief
  • B. Business Case
  • C. Project Initiation Documentation
  • D. Project Product Description
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
timedout
3 years, 1 month ago
A - Project Brief (see Figure 15.2)
upvoted 3 times
...
Adeey
3 years, 7 months ago
This should be this PID
upvoted 1 times
Andreas1975
3 years, 6 months ago
I believe PID is used to authorize the project, not to authorize initiation
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...