Exam PRINCE2-Foundation topic 1 question 186 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 186
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a factor when deciding the duration of a management stage?

  • A. The work packages to be delivered
  • B. The level of risk in the project
  • C. The cost of the stage
  • D. The number of products to be produced in the project
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.prince2primer.com/the-design-of-prince2-management-stages/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Jasonbahr
Highly Voted 2 years, 3 months ago
B is correct. "The number of management stages within a project is clearly a balance between risk and cost as well as other factors. For example a high risk project would tend to have shorter management stages since the project board would want to review progress and the overall project status more often."
upvoted 7 times
...
SGN63
Most Recent 4 months ago
Selected Answer: B
B is correct
upvoted 2 times
...
peppe
1 year, 9 months ago
B is correct
upvoted 2 times
...
Martin77
2 years, 3 months ago
B is correct, according to the linked resource - " By observing which risks may occur in which of the management stages, decisions can be made about end stage assessment points and stage duration."
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago