Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 105 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 105
Topic #: 1
[All PRINCE2-Foundation Questions]

Which of the following statements about quality assurance and Project Assurance is true?

  • A. Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
  • B. Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
  • C. Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
  • D. Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Jasonbahr
Highly Voted 3 years, 7 months ago
It is important not to confuse quality assurance with project assurance: Quality assurance provides a check that the project's direction and management are adequate for the nature of the project and that it complies with relevant corporate, programme management or customer standards and policies. Quality assurance is therefore independent of the project. Project assurance is the project board's responsibility to assure itself that the project is being conducted correctly. The project board members each have a specific area of focus for project assurance, namely business assurance for the executive, user assurance for the senior user(s) and supplier assurance for the senior supplier(s). Project assurance is therefore independent of the project manager but not independent of the project. So D is the correct answer.
upvoted 16 times
KeanoD
2 years, 3 months ago
Excellent explanation, thank you for that
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...