The objective of the closing a project process is to:
verify user acceptance of the project's products
ensure that the host site is able to support the products when the project is disbanded
review the performance of the project against its baselines
assess any benefits that have already been realized and update the benefits management approach to include any post-project benefit reviews
ensure that provision has been made to address all open issues and risks, with follow-on action recommendations.
correct, "In consultation with the project management team, prepare follow-on action recommendations for the project’s products to include any uncompleted work, issues and risks. There could be separate follow-on action recommendations for each product or distinct user group (e.g. human resources, finance, operations)."
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Jasonbahr
Highly Voted 3 years, 7 months agopeppe
Most Recent 3 years, 1 month agopeppe
3 years, 1 month agokal5
3 years, 2 months ago